Construction at Burnham Waters continues to progress well as we enjoy the summer weather. We are pleased to say the construction site has been set up and works are progressing on time.
Construction updates
As of present:
- The site has been stripped of all topsoil to the south side of the ditch. This is the first phased area of development.
- Installation of the foul and surface water drainage are the first elements of works and is currently under construction.
- Following this, will be the forming of the roads.
- The foul water drainage in roads 1, 2 and 8 is now complete from the site entrance off Maldon Road up to plot 25; this has allowed us to cut and form the same roads and tarmac is due to be laid at the end of August. The culvert beneath road 11 where it crosses the ditch is also complete!
- Foundation works to the bungalows are due to commence on 22nd August 2022.
We are extremely excited to see the construction steps move along at pace. It's another step closer to welcoming our new residents to Burnham Waters.